Shatin to Central Link and MTR Kwun Tong Line Extension



DateContextSummary of developmentAction
31.5.00 CQ Hon Andrew CHENG raised a question on Sha Tin - Central Rail Corridor. [Hansard "page 55"]
6.12.00 CM A motion moved by Hon LAU Chin-shek's motion as amended by Hon LAU Kong-wah and Dr Hon TANG Siu-tong on railway development strategy was passed. [Motion "page 159"]
14.3.01 CQ Hon LAU Kong-wah raised a question on early completion of rail link from Sha Tin to Central. [Hansard "page 60"]
6.12.01 SUBC SUBC discussed the progress report of the latest situation regarding the bidding of the Shatin to Central Link (SCL). [Paper]

Development to date presented in background brief prepared by the Secretariat. [Paper]

27.6.02 SUBC SUBC discussed paper on the Executive Council on 25.6.02. The Council ADVISED and the Chief Executive ORDERED that the SCL should be awarded to Kowloon-Canton Railway Corporation (KCRC). [LegCo Brief]
10.7.02 CQ Hon Fred LI raised a question on railway alignment of SCL. [Hansard "page 99"]
27.9.02 SUBC The Administration informed SUBC of the latest progress regarding SCL. [Paper]
26.2.03 CQ Hon Abraham SHEK raised a question on selection of railway corporation to operate the new Shatin to Central Link. [Hansard "page 15"]
7.5.03 PWSC PWSC endorsed the funding proposal on Central Government Complex (CGC), Legislative Council Complex (LCC), exhibition gallery and civic place at Tamar, Central and planning and Infrastructure Exhibition Gallery at Tamar - exhibits design and fabrication. [Paper]
5.03 TP The Administration provided the Panel with a paper which set out the security considerations in the planning of the new development at Tamar vis-à-vis the alignment of SCL and other public transport services in the vicinity. [Paper]
18.7.03 SUBC SUBC discussed the further information on the implication of the decision not to allow for any railway station or tunnel directly underneath CGC and LCC at Tamar on the planning and implementation of SCL, and the resulting financial implication. [Paper]
29.9.03 SUBC SUBC discussed the Administration's paper which provided the latest update on SCL and addressed the enquiries raised by members at the meeting on 1.8.03. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Paper]

18.2.04 PWSC PWSC endorsed a commitment to upgrade part of 469CL to Category A at an estimated cost of $119.1 million in money-of-the-day (MOD) prices to carry out site preparation and infrastructure works in the north apron area of the former Kai Tak Airport to prepare the site for future developments including SCL. [Paper]
24.2.04 PRESS Members of the Transport Advisory Committee were briefed on the latest progress of SCL. [Press Release]
27.2.04 FC FC approved the commitment endorsed by PWSC on 18.2.04. [Paper]
7.5.04 SUBC SUBC discussed the progress of SCL. [Paper]
16.2.04 SUBC The Subcommittee discussed the progress on the scheme design of the SCL. [Paper], [Follow-up paper]
4.3.05 SUBC SUBC discussed with the Administration the current position of the SCL. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

5.1.07 SUBC SUBC discussed with the Administration the current position of the proposed SCL. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

14.3.07 CQ Hon Federick FUNG Kin-kee raised a question on construction of the SCL. [Hansard "page 81"]
16.7.07 SUBC SUBC discussed with the Administration the latest progress of the planning of the SCL project. [Paper]
24.10.07 CQ Hon Alan LEONG kah-kit raised a question on SCL. [Hansard "page 36"]
31.10.07 CQ Hon TAM Heung-man raised a question on SCL depot. [Hansard "page 8"]
27.3.08 SUBC Government issued a LegCo Brief on Shatin to Central Link and MTR Kwun Tong Line Extension. [LegCo Brief]

SUBC discussied with the Administration on Shatin to Central Link and MTR Kwun Tong Line Extension. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

9.4.08 CQ Hon CHAN Yuen-han raised a question on construction of the Shatin to Central Link depot at Diamond Hill. [Hansard "page 66"]
23.4.08 PWSC PWSC endorsed a commitment to upgrade 51TR to Category A at an estimated cost of $2,407.5 million in money-of-the-day prices for the design and site investigation of the Shatin to Central Link. [Paper]
9.5.08 FC FC approved the commitment endorsed by PWSC on 23.4.08. [Paper]
31.3.09 SUBC SUBC met deputations and received views on SCL.

SUBC discussed paper on SCL.[Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

17.9.09 SUBC The SUBC discussed the Kwun Tong Line Extension with the Administration. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

28.10.09 CQ Hon James TO Kun-sun raised a question on Shatin to Central Link development projects in the Kai Tak Development area. [Hansard "page 19"]
18.11.09 CQ Hon Mrs Regina IP LAU Suk-yee raised a question on Shatin to Central Link. [Hansard "page 89"]
16.12.09 CQ Hon Starry LEE Wai-king raised a question on Kwun Tong Line Extension. [Hansard "page 81"]
20.1.10 CQ Hon Starry LEE Wai-king raised a question on Shatin to Central Link. [Hansard "page 80"]
16.4.10 SUBC The SUBC discussed the progress report on the Kwun Tong Line Extension with the Administration. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

4.6.10 SUBC The SUBC discussed the funding application - protection works for Shatin to Central Link in Wan Chai Development Phase II with the Administration. [Paper]
9.6.10 PWSC PWSC endorsed a commitment to upgrade part of 58TR relating to "Shatin to Central Link - construction of railway works - protection works in Wan Chai Development Phase II" to Category A, at an estimated cost of $152.6 million in money-of-the-day prices. [Paper]
2.7.10 FC FC approved a commitment endorsed by PWSC on 9.6.10. [Paper]
6.7.10 SUBC The SUBC discussed the progress report on the Kwun Tong Line Extension with the Administration. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

14.7.10 SUBC The SUBC met deputations and received views.
4.11.10 SUBC The SUBC discussed the progress report on the Shatin to Central Link with the Administration. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

6.12.10 SUBC The SUBC discussed Shatin to Central Link - Remaining Protection Works and Advance Works with the Administration. [Paper]

Development to date presented in background brief prepared by the Secretariat. [Background brief]

The SUBC discussed the Kwun Tong Line Extension with the Administration. [LegCo Brief] [Paper]

16.12.10 SUBC The SUBC further discussed on progress report of Kwun Tong Line Extension and funding application for Essential Public Infrastructure Works with the Administration. [LegCo Brief] [Paper]
7.1.11 SUBC The SUBC further discussed the funding application related to the advance works for Shatin to Central Link with the Administration. [Paper]
19.1.11 PWSC PWSC endorsed a commitment to upgrade 60TR to Category A at an estimated cost of $826.9 million in money-of-the-day prices for the essential public infrastructure works for the Kwun Tong Line Extension. [Paper]
25.1.11 PWSC PWSC endorsed a commitment to upgrade part of 61TR entitled "Shatin to Central Link - construction of railway works - advance works", to Category A at an estimated cost of $6,254.9 million in money-of-the-day prices. [Paper]
25.1.11 PWSC PWSC endorsed a commitment to upgrade part of 62TR entitled "Shatin to Central Link - construction of non-railway works - advance works", to Category A at an estimated cost of $1,448.2 million in money-of-the-day prices. [Paper]
18.2.11 FC FC approved a commitment endorsed by PWSC on 19 & 25.1.11. [Paper]
6.5.11 SUBC The SUBC discussed the funding application - protection works at Causeway Bay typhoon shelter for Shatin to Central Link with the Administration. [Paper]
1.6.11 PWSC PWSC endorsed a commitment to upgrade 58TR to Category A at an estimated cost of $541.6 million in money-of-the-day prices for the construction of protection works for the Shatin to Central Link tunnel at Causeway Bay Typhoon Shelter. [Paper]
24.6.11 FC FC approved a commitment endorsed by PWSC on 1.6.11. [Paper]
6.7.11 CQ Hon CHAN Hak-kan raised a question on possible delay of the Shatin to Central Link project. [Hansard "page 126"]
2.3.12 SUBC The SUBC discussed Shatin to Central Link - Progress report with the Administration. [Paper] [Follow-up paper]

Development to date presented in background brief prepared by the Secretariat. [Updated background brief]