| Chapter | Page | |
|---|---|---|
| I. | Introduction | 1 - 3
|
| II. | Tin Chung Court incident - Background and management structure
| |
| Background | 4 - 6
| |
| Management structure for the project | 6 - 13
| |
| III. | Tin Chung Court - Planning and design
| |
| Ground conditions of the Tin Chung Court site | 14 - 15
| |
| Piling design | 15 - 24
| |
| IV. | Tin Chung Court - Construction
| |
| Work stages and technical requirements | 25- 39
| |
| Supervision of works on site | 40 - 44
| |
| V. | Tin Chung Court - Verification of piling design | 45 - 53
|
| VI. | Tin Chung Court - Division of responsibilities in quality assurance | 54 - 59
|
| VII. | Conclusions and recommendations on the Tin Chung Court incident
| |
| General Conclusions | 60 - 70
| |
| Responsibility of the parties concerned | 70 - 75
| |
| Concluding remarks | 75 - 76
| |
| Further recommendations | 76 - 80
| |
| Acknowledgement | 81
| |
| Signatures of Members of the Select Committee | 82 - 83
| |
| Abbreviations | 87 - 89 | |
| Page | ||
| Appendices | ||
| Appendix 1 | Membership list | 93
|
| Appendix 2 | List of Witnesses Appearing before the Select Committee to Give Evidence in Relation to Tin Shui Wai Area 31 Phase 1 Incident | 94 - 96
|
| Appendix 3 | Tin Shui Wai Area 31 Phase 1 General Layout Plan | 97
|
| Appendix 4 | Chronology of Important Activities Relating to Tin Shui Wai Area 31 Phase 1 Piling Contract | 98 - 101
|
| Appendix 5 | Summary of the Results of Investigatory Works to Ascertain the Founding Depths of a Number of Piles at Blocks 1 and 2 | 102
|
| Appendix 6 | Organization Chart Showing the Key Personnel Responsible for Piling Contract No. 36/96 Tin Shui Wai Area 31 Phase 1 | 103
|
| Appendix 7 | Chronology of the Recruitment of Resident Engineer for Tin Shui Wai Area 31 Phase 1 | 104 - 106
|
| Appendix 8 | Locations of the 53 Boreholes Sunk by Acer Consultants (Far East) Ltd. | 107
|
| Appendix 9 | The Layers of Soil underneath Blocks 1 and 2 according to the Acer Report | 108 - 109
|
| Appendix 10 | Locations of the 24 Boreholes Numbering HY1 to HY24 | 110
|
| Appendix 11 | Static Calculations for Piling Design of Block 1 | 111 - 114
|
| Appendix 12 | Particular Specification 19.43 | 115
|
| Appendix 13 | Locations of Preliminary Piles | 116
|
| Appendix 14 | Sequence of Final Set of Piles in Block 1 | 117
|
| Appendix 15 | Locations of Boreholes Used in Calculating Settlement of Block 2 | 118
|
| Lists of Written Evidence | 121 - 139
| |
| Minutes of Proceedings | 143 - 148 | |
| Date | Public Hearings | Witness | Volume |
|---|---|---|---|
| The 1st to 19th hearings are in relation to Policies and Working Mechanismsfor the Production of Housing Units Subject to and Exempted fromthe Buildings Ordinance which are not covered by the Second Report. | |||
| 11 September 2001 | 20 | Mr Stephen POON Sing-chi Former Senior Assistant Director/New Development Housing Department | IIA
|
| 13 September 2001 | 21 | Part I Mr Stephen POON Sing-chi Former Senior Assistant Director/New Development Housing Department | IIA |
| Part II Ir Alan CLOVER Ir Rupert LEUNG Kwok-yiu Representatives of Hyder Consulting Ltd (formerly known asAcer Consultants (Far East) Ltd) | IIA
| ||
| 18 September 2001 | 22 | Mr Joseph KONG Churk-fan Chief Architect for Tin Shui Wai Area 31 Phase 1 project | IIA
|
| 20 September 2001 | 23 |
Mr YUEN Tze-chu Director's Representative for Tin Shui Wai Area 31 Phase 1 project | IIA
|
| 25 September 2001 | 24 | Part I Mr Tommy IP Kwok-wing Quantity Surveyor for Tin Shui Wai Area 31 Phase 1 project | IIA |
| Part II Mr David LEE Sai-cheung Chief Structural Engineer for Tin Shui Wai Area 31 Phase 1 project | IIA
| ||
| 27 September 2001 | 25 | Mr David LEE Sai-cheung Chief Structural Engineer for Tin Shui Wai Area 31 Phase 1 project | IIA |
| The 26th hearing was held in camera. | |||
| 9 October 2001 | 27 | Part I Mr Joseph HO Mr Conrad CHENG Yuk-keg Representatives of Hsin Yieh Architects & Associates Ltd | IIB |
| Part II Mr NG Hon-keung Mr MAK Lap-ming Representatives of Joseph Chow & Partners Limited (JMK Consulting Engineers) | IIB
| ||
| 16 October 2001 | 28 | Mr HO Sau-him Director's Representative for Tin Shui Wai Area 31 Phase 1 project | IIB
|
| The 29th hearing was held in camera. | |||
| 23 October 2001 | 30 |
Part I Mrs Rosa HO LOK So-fun Liaison Senior Architect for Tin Shui Wai Area 31 Phase 1 project Ms Rosman WAI Chui-chi Liaison Senior Architect for Tin Shui Wai Area 31 Phase 1 project Mr LI Kar-fai Liaison Architect for Tin Shui Wai Area 31 Phase 1 project | IIB |
| Part II Mr Francis LEE Kam-chuen Liaison Senior Structural Engineer for Tin Shui Wai Area 31 Phase 1 project | IIB | ||
| The 31st hearing was held in camera. | |||
| 30 October 2001 | 32 | Mr Chezy TANG Wai-chau Former Project Structural Director Hsin Yieh Architects & Associates Ltd | IIB
|
| 3 November 2001 | 33 | Mr NG Hon-keung Mr MAK Lap-ming Representatives of Joseph Chow & Partners Limited (JMK Consulting Engineers) | IIB
|
| The 34th to 35th hearings were held in camera. | |||
| 13 November 2001 | 36 | Part I Mr SUEN Pak-chiu Geotechnical Engineer for Tin Shui Wai Area 31 Phase 1 project | IIB |
| Part II Mr WONG Chi-ming Representative ofC M Wong & Associates Ltd | IIB
| ||
| The 37th hearing was held in camera. | |||
| 20 November 2001 | 38 | Mr NG Hon-keung Mr MAK Lap-ming Representatives of Joseph Chow & Partners Limited (JMK Consulting Engineers) | IIB |
| The 39th to 41st hearings were held in camera. | |||
| The 42th to 64th and 68th hearings are in relation to Shatin Area 14B Phase 2, Shek Yam Estate Phase 2 and Tung Chung Area 30 Phase 3 projects which are not covered by the Second Report. | |||
| The 65th to 67th and 69th hearings are in relation to Policies and Working Mechanisms for the Production of Housing Units Subject to and Exempted from the Buildings Ordinance which are not covered by the Second Report. | |||
| The 70th hearing was held in camera. | |||