LC Paper No.PaperMeeting date
PWSC(2016-17)43 Shatin to Central Link - construction of railway works - advance works 25 January 2017
3 February 2017
15 February 2017
18 February 2017
22 February 2017
16 March 2017
22 March 2017
5 April 2017
PWSC111/16-17(01) Letter dated 16 March 2017 from Hon Jeremy TAM Man-ho to the Chairman regarding PWSC(2016-17)43 - Shatin to Central Link - construction of railway works - advance works (Chinese version only) 22 March 2017
PWSC114/16-17(01) Administration's response to the request made by members at the meeting on 16 March 2017 for further information about PWSC(2016-17)43 and a letter from Hon Jeremy TAM regarding PWSC(2016-17)43 - Shatin to Central Link - construction of railway works - advance works 22 March 2017
PWSC114/16-17(02) Letter dated 22 March 2017 from Hon CHU Hoi-dick to the Chairman of the Public Works Subcommittee regarding PWSC(2016-17)43 - Shatin to Central Link - construction of railway works - advance works (Chinese version only) 22 March 2017
PWSC117/16-17(01) Second letter (dated 23 March 2017) from Hon Jeremy TAM Man-ho to the Chairman regarding PWSC(2016-17)43 - 63TR - Shatin to Central Link - construction of railway works - advance works (Chinese version only) 22 March 2017
5 April 2017
PWSC128/16-17(01) Administration's response to the request made by members at the meeting on 22 March 2017 for further information about PWSC(2016-17)43 - Shatin to Central Link - construction of railway works - advance works and letters from Hon CHU Hoi-dick and Hon Jeremy TAM regarding PWSC(2016-17)43 22 March 2017
PWSC128/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)43 - Shatin to Central Link - construction of railway works - advance works (English version only) 22 March 2017
PWSC152/16-17(01) Administration's response to the request made by members at the meeting on 5 April 2017 for supplementary information about PWSC(2016-17)43 - Shatin to Central Link - construction of railway works - advance works 5 April 2017
PWSC(2016-17)44 South Island Line (East) - essential public infrastructure works 25 January 2017
3 February 2017
15 February 2017
18 February 2017
22 February 2017
16 March 2017
22 March 2017
5 April 2017
12 April 2017
20 April 2017
PWSC133/16-17(01) Administration's response to the request made by Hon KWONG Chun-yu at the meeting on 5 April 2017 for further information about PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works 12 April 2017
PWSC127/16-17(01) Letter dated 5 April 2017 to the Chairman from Hon CHU Hoi-dick regarding PWSC(2016-17)43 - 63TR - Shatin to Central Link - construction of railway works - advance works and PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Chinese version only) 12 April 2017
PWSC132/16-17(01) Administration's response to a letter dated 5 April 2017 from Hon CHU Hoi-dick to the Chairman regarding PWSC(2016-17)43 - 63TR - Shatin to Central Link - construction of railway works - advance works and PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works 12 April 2017
PWSC133/16-17(03) Letter dated 12 April 2017 from Hon CHU Hoi-dick to the Chairman regarding PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Chinese version only) 12 April 2017
PWSC138/16-17(02) Administration's response to a letter dated 12 April 2017 from Hon CHU Hoi-dick to the Chairman regarding PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works 20 April 2017
PWSC138/16-17(01) Administration's response to the request made by Dr Hon YIU Chung-yim at the meeting on 12 April 2017 for supplementary information about PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works 20 April 2017
PWSC138/16-17(03) Letter dated 20 April 2017 from Hon CHU Hoi-dick to the Chairman, the Secretary for Transport and Housing and the Chairman of the MTR Corporation Limited regarding PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Chinese version only) 20 April 2017
PWSC178/16-17(01) Administration's response to a letter dated 20 April 2017 from Hon CHU Hoi-dick to the Chairman, the Secretary for Transport and Housing and the Chairman of the MTR Corporation Limited regarding PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 1 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 2 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 3 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 4 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 5 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 6 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 7 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 8 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 9 of 10) (English version only) 20 April 2017
PWSC178/16-17(02) Full set of information contained in the ground investigation report provided by the MTR Corporation Limited in relation to PWSC(2016-17)44 - 56TR - South Island Line (East) - essential public infrastructure works (Part 10 of 10) (English version only) 20 April 2017