At the Enclosure is a summary of the recommendations of the Public Works Subcommittee (PWSC) made at its meeting on 17 April 1996. The relevant papers have previously been forwarded to all Members for consideration by the PWSC and are therefore not enclosed.

2. Members are invited to approve the PWSC recommendations.

Finance Branch
April 1996


Enclosure to FCR(96-97)6

Summary of the Recommendations of the Public Works Subcommittee discussed at the meeting on 17 April 1996

Project code Project description Recommendation

75CD
PWSC(96-97)1
(Head 704)

Stormwater drainage master plan study on northern Hong Kong Island

To recommend to Finance Committee the upgrading of 75CD to Category A at an estimated cost of $22.5 million in money-of-the-day prices.

66CL
PWSC(96-97)2
(Head 707)

Sha Tin New Town, stage II - engineering development, package 23, phase 2

To recommend to Finance Committee an increase in the approved project estimate of 66CL from $1,232 million by $294.8 million to $1,526.8 million in money-of-the-day prices.

409CL
PWSC(96-97)3
(Head 707)

Sha Tin New Town - stage II : servicing and extension of Chap Wai Kon, Ngau Pei Sha and To Shek Villages in area 35

To recommend to Finance Committee an increase in the approved project estimate of 409CL from $53 million by $40.9 million to $93.9 million in money-of-the-day prices.