For discussion
FCR(97-98)88
on 16 January 1998

ITEM FOR FINANCE COMMITTEE

RECOMMENDATIONS OF THE PUBLIC WORKS SUBCOMMITTEE ON PUBLIC WORKS PROGRAMME AND CAPITAL SUBVENTION PROJECTS

At the Enclosure is a summary of the recommendations of the Public Works Subcommittee (PWSC) made at its meeting on 10 December 1997. The relevant papers have previously been forwarded to all Members for consideration by the PWSC and are therefore not enclosed.

2. Members are invited to approve the PWSC recommendations.


Finance Bureau

December 1997


Enclosure to FCR(97-98)88

Summary of the Recommendations of the Public Works Subcommittee made at its meeting on 10 December 1997

Project code

Project description


Recommendation

196EP

PWSC(97-98)86 (Head 711)

Primary school in area 105, Tin Shui Wai


To recommend to Finance Committee the upgrading of 196EP to Category A at an estimated cost of $81.3 million in money-of-the-day prices for the construction of a primary school in area 105, Tin Shui Wai.

6GB

PWSC(97-98)87 (Head 703)

Expansion of kiosks and other facilities at Lok Ma Chau boundary crossing


To recommend to Finance Committee -

(a) the upgrading of part of 6GB as 7GB, entitled "Expansion of kiosks and other facilities at Lok Ma Chau boundary crossing - pre-contract consultancy and design" to Category A at an estimated cost of $104.1 million in money-of-the-day prices; and

(b) the retention of the remainder of 6GB retitled "Expansion of kiosks and other facilities at Lok Ma Chau boundary crossing - works" in Category B.

120WC

PWSC(97-98)88 (Head 711)

Extension of Shau Kei Wan high level water supply systems


To recommend to Finance Committee the upgrading of 120WC to Category A at an estimated cost of $219.3 million in money-of-the-day prices for the construction of a fresh water service reservoir, a salt water service reservoir, associated water mains and upgrading of an existing pumping station in Shau Kei Wan.

121WC

PWSC(97-98)89 (Head 711)

Extension of water supply to Ma On Shan


To recommend to Finance Committee the upgrading of 121WC to Category A at an estimated cost of $268.2 million in money-of-the-day prices for the construction of a fresh water service reservoir, a salt water service reservoir and associated watermains in Ma On Shan.

117GK

PWSC(97-98)90 (Head 705)

Explosives Complex at Kau Shat Wan, building, mechanical and electrical works


To recommend to Finance Committee an increase in the approved project estimate of 117GK from $249.7 million by $39.8 million to $289.5 million in money-of-the-day prices.

45DR

PWSC(97-98)91 (Head 705)

Restoration of Northwest New Territories landfills, Part 2 and the Gin Drinkers Bay landfill


To recommend to Finance Committee -

(a) the upgrading of part of 45DR as 158DR, entitled "Restoration of Gin Drinkers Bay landfill - works", to Category A at an estimated cost of $273.5 million in money-of-the-day prices; and

(b) the retention of the remainder of 45DR in Category B, retitled "Restoration of Pillar Point Valley landfill".

54BL

PWSC(97-98)92 (Head 704)

Investigation of sewers and drains affecting the safety of cut slopes


To recommend to Finance Committee the upgrading of 54BL to Category A at an estimated cost of $57.6 million in money-of-the-day prices for the engagement of consultants to investigate the physical conditions of public sewers and drains buried behind and adjacent to cut slopes.