Provisional Legislative Council
Panel on Financial Affairs
and
Panel on Transport
Equity Injection for Implementation of West Rail Phase I Project

Purpose

This paper briefs Members on the intended submission to Finance Committee for approval, subject to the enactment of the Kowloon-Canton Railway Corporation (Amendment) Bill 1998, of a commitment to inject equity of $29,000 million from the Capital Investment Fund into the Kowloon-Canton Railway Corporation, to allow major works on West Rail Phase I to proceed. A copy of the draft Finance Committee agenda item for the meeting on 27 February is enclosed for Members’ information.

2. The Administration will be pleased to discuss its proposals and to answer any questions that Members may have on these at the joint meeting of the Panels on 12 February 1998.

Finance Bureau
February 1998

DRAFT

For discussion
on 27 February 1998

FCR(97-98)

ITEM FOR FINANCE COMMITTEE

CAPITAL INVESTMENT FUND
NEW HEAD - KOWLOON-CANTON RAILWAY CORPORATION
New Subhead "West Rail Phase I"

PROBLEM

We need to inject equity into the Kowloon-Canton Railway Corporation (KCRC) to enable it to construct West Rail Phase I (WR).

PROPOSAL

2. We propose that Members approve a commitment of $29,000 million from the Capital Investment Fund (CIF) as equity to be injected into KCRC. This approval will be subject to the enactment of the KCRC (Amendment) Bill 1998 which was introduced into the Provisional Legislative Council on 11 February 1998 and which provides, inter alia, for the Corporation to have a proper share capital structure and the powers to undertake authorised new railway projects.

JUSTIFICATION

KCRC's Business Plan

3. To help Members assess the nature of the proposed investment in the WR project, KCRC has prepared a Business Plan for WR covering the following matters –

  1. Project Costs

  2. Property Development

  3. Financial Projection

  4. Corporation Financial Plan

  5. Financing Strategy.

A copy of the Business Plan is at Enclosure 1. Major issues in the Business Plan are highlighted as follows.

Cost estimate for WR

4. KCRC's latest total project cost estimate is $64 billion, broken down as follows–

$billion
(money of the day)
Capital costs51.0
Land acquisition costs7.9
Financing costs5.1
_________
Total 64.0
_________

Government's assessment

5. Government's consultants have independently assessed KCRC's capital cost estimates and confirmed that the overall cost estimates are within an acceptable range. The Lands Department has also advised that KCRC's base estimate for the land acquisition costs, from which the above money of the day (MOD) figure is derived, is not unreasonable. These figures do not however take into account additional costs that may arise due to development of the airspace above any locations along the WR alignment (please refer to paragraph 9 below).

Financing arrangements

6. The total project costs are intended to be financed as follows–

$billion
Borrowings24.9
Internal resources10.1
Government equity 29.0
_______
Total64.0
_______

Government's assessment

7. Government's financial consultants have confirmed that KCRC has the ability to raise commercial loans of $24.9 billion at a corporate level and the estimated financing costs are reasonable. As for KCRC's internal resources, they will come from its East Rail and Light Rail property development profits and interest earnings. The remaining requirement to be funded by Government in the form of equity is roughly equal to half of the total project cost estimate. Our financial consultants have advised that this amount should provide KCRC with a reasonably strong equity base in comparison with the loans to be raised and also let KCRC have sufficient flexibility in arranging its finances. The amount also gives a clear signal to the financial market about the extent of Government commitment to the project which should further strengthen the confidence of lenders in providing loans to KCRC. It will not be appropriate to provide more equity than optimally required under the financing proposal, as equity is generally a more expensive means of financing than commercial borrowing. More equity also means fewer opportunities for private sector participation in the financing of the railway projects.

Project Evaluation

8. KCRC's latest estimate for the project internal rate of return (IRR) of West Rail is 8.9%. KCRC and our financial consultants have also run some sensitivity tests to examine various upside and downside scenarios. These result in project IRR estimates ranging from 8.2% to 11%, which are comparable with the projected 10% for the Airport Railway and MTRC's estimate of 8.5% for the Tseung Kwan O Extension. On the basis of these figures, we are reasonably confident that West Rail will be a commercially viable project. The proposed equity injection of $29 billion into KCRC should therefore be a prudent investment.

Property Development

9. For WR financing purposes, KCRC will continue to be allowed to make use of the development potential along its East Rail and Light Rail alignments so that the profits derived can be applied towards meeting the project costs. In respect of property developments along WR, KCRC will be allowed to undertake these developments so as to ensure the timely delivery of housing supply, better integration with the neighbourhood and smooth interface with railway operations. However, as these developments will go beyond the time frame for the WR project and KCRC can achieve a satisfactory project internal rate of return without the stream of profits from WR developments, KCRC will require the profits neither for financing the project nor for improving the project return. Therefore, we intend and KCRC has accepted that it should pass on the net (i.e. exclusive of KCRC's contingent expenses and, if necessary, any additional development-related costs) WR property development profits to Government directly as soon as they are realised, rather than treating them as windfall profits.

Draft Project Agreement

10. On the basis of the Business Plan and our assessment above, a draft Project Agreement was drawn up between KCRC and Government. The draft Project Agreement sets out how the WR project will be undertaken and the respective obligations of both parties in terms of the financing, design, construction and operation of WR. A clause by clause explanation of the draft Project Agreement is at Enclosure 2.

Upfront equity injection

11. In order to complete WR in a timely and cost effective manner, KCRC needs substantial resources to continue to take forward the project. As KCRC has steadily invested its existing resources to advance the technical studies for the project and the project outlays in 1998 and 1999 are estimated to be some $2 billion and $13.9 billion respectively, we have agreed to inject equity into the KCRC upfront so as to alleviate its resource constraints and help take forward the project according to the tight implementation time-table. The upfront injection of equity, together with KCRC's internal resources to be generated in the next few years, will also enable KCRC to defer its commercial borrowings to a later stage of the project, around the year 2000, thereby minimising its financing costs. The proposed upfront equity injection will commence following the enactment of the KCRC (Amendment) Bill 1998.

Impact of WR on fare levels for existing lines

12. KCRC has indicated that the fare policy for WR will be developed independently of its existing businesses on the basis of prudent commercial principles, having regard to such factors as affordability and competition with other transport modes. Thus, KCRC would not adjust fares for passengers using its existing lines to subsidise the operations of WR.

FINANCIAL IMPLICATIONS

13. Subject to Members’ approval, we will inject the equity in question into KCRC by two equal instalments of $14,500 million each, with the first in May 1998 and the second approximately a year later.

14. We will also need to carry out some essential public infrastructure works throughout the construction period of WR in the order of $3,135 million in 1997 prices to enable West Rail to be open to the public. Such works include the provision of feeder roads, construction of public transport interchanges, reclamation etc. They will be entrusted to KCRC and their costs will be reimbursed by Government, through funding from the Capital Works Reserve Fund. Funding approval for these works will be sought separately from the legislature in due course.

ENVIRONMENTAL IMPLICATIONS

15. KCRC completed an Initial Environmental Impact Assessment (IEIA) on WR in August 1997. The study indicated that operational train noise and ecological impact at Kam Tin Valley were the major environmental concerns and concluded that with the implementation of mitigation measures the impacts would not be insurmountable. The IEIA was endorsed by the Advisory Council on the Environment (ACE) in September 1997. KCRC is now finalising the EIA study and will consult ACE again on the findings in due course. KCRC has agreed that work will not commence until ACE is fully consulted. KCRC is committed to implementing all the mitigation measures and environmental monitoring and audit programme recommended in the EIA study.

BACKGROUND INFORMATION

16. West Rail (previously known as the Western Corridor Railway) is one of the three priority railway projects recommended in the 1994 Railway Development Strategy. On 13 December 1996, the former Legislative Council was briefed that–

  1. the route proposed by KCRC should be adopted;

  2. the construction should proceed in two phases – with Phase I, comprising the domestic passenger line from West Kowloon via Tsuen Wan, Kam Tin, Yuen Long and Tin Shui Wai to Tuen Mun built first, leaving cross boundary passenger and freight services (Phase II) to a later date;

  3. the issues of cross boundary passenger and freight services should be discussed with the Mainland authorities concerned; and

  4. KCRC should continue technical studies, with a view to drawing up a project agreement.

17. In accordance with the project programme and under the Railways Ordinance, Government gazetted Phase I of West Rail in two stages, on 25 July 1997 and 3 October 1997 respectively. Slightly over 200 objections have been received. The majority of these objections relate to land matters and compensation issues. Under the Railways Ordinance, these objections will be handled within a period of nine months upon the expiry of the 60 days objection period. The relevant railway schemes and any unwithdrawn objections will then be submitted to the Executive Council for consideration by September 1998. Pending the authorisation of the schemes by the Executive Council, the WR Project Agreement which sets out the main terms and conditions for KCRC to undertake the project will be executed. KCRC will design and complete the construction of WR in order to bring the railway into operation by the Scheduled Operating Date, targeted at December 2003, and thereafter to operate and maintain the railway for 50 years.

Finance Bureau
February 1998

(FIN CR 1/986/95)

Draft Project Agreement
for the
Financing, Design, Construction and Operation of West Rail
between
The Government of the Hong Kong Special Administrative Region
and
The Kowloon-Canton Railway Corporation
Clause by Clause Explanation

Introduction

1. The Project Agreement is divided into eleven parts with four appendices. The eleven parts cover interpretation, financing, property developments, scope of works, planning, design and construction, programme and progress, operation and maintenance, land matters, environmental protection, transport, project monitoring and accounts and miscellaneous provisions. The Project Agreement is intended to form a binding contract between Government and the Corporation. It sets out clearly, and also delimits, the precise obligations of Government to the Corporation and vice versa.

Recitals

2. The recitals set out the general scope and purpose of the Project Agreement. They refer to matters addressed prior to the date of the Project Agreement. Such matters include:

  1. the amendment of the Kowloon-Canton Railway Corporation Ordinance (Cap. 372 of the Laws of Hong Kong) pursuant to the enactment of the Kowloon-Canton Railway Corporation (Amendment) Ordinance 1998 (No. [ ] of 1998 of the Laws of Hong Kong) (the "KCRC Ordinance");

  2. the authorisation of the scheme in respect of West Rail in accordance with the Railways Ordinance (Cap. 519 of the Laws of Hong Kong); and

  3. the agreement between Government and the Corporation to enter into the Project Agreement to provide for the financing, design, construction and operation of West Rail and related services and facilities.

Part I - Interpretation

3. The interpretation section sets out definitions of specialised terms used in the Project Agreement. These ensure precision and consistency in the terms used with a view to ensuring that there is no misunderstanding as to the duties and obligations of the parties.

Part II - Financing of West Rail

4. This section sets out the financial support to be provided by Government to the Corporation. The main provisions are as follows:

Part III - Property Developments

5. This section sets out the arrangements for dealing with property development rights along the East Rail, the Light Rail and West Rail.

Part IV - Scope of Works, Planning, Design and Construction

6. This section deals with the obligations of the Corporation and Government in respect of the design, construction, completion, testing, commissioning, operation and maintenance of West Rail. These obligations need to be clearly set out to enable financiers to make a proper evaluation of the Corporation's creditworthiness.

Part V - Programme and Progress

7. This part deals with the obligation of the Corporation to complete West Rail in accordance with the Baseline Programme and to commence Commercial Operations by the Scheduled Operating Date. It demonstrates Government's involvement in the programme timing and ability to monitor the progress of the Scope of Works against the Baseline Programme.

Part VI - Operation and Maintenance

8. This part deals with the obligations of the Corporation for the operation and maintenance of West Rail.

Part VII - Land

9. The arrangements regarding land to be entered into between Government and the Corporation, the land rights to be granted by Government to the Corporation and the commercial activities at West Rail stations are set out in this part. It demonstrates Government's commitment to make the West Rail project viable.

Part VIII - Environmental Protection

10. This part sets out the environmental protection matters applicable to the West Rail project.

Part IX - Transport

11. This part deals with the commitment of Government and the Corporation to encourage use of West Rail.

Part X - Project Monitoring and Accounts

12. This part sets out the right of Government to appoint a monitoring committee in relation to the West Rail project and deals with the obligations of the Corporation to cooperate with such committee and to maintain and submit to Government upon request books, accounts and records in connection with the West Rail project.

Part XI - Miscellaneous

13. This section covers other matters of essential legal detail obtained in contracts.

Clause 30 clarifies that the development of West Rail under the Project Agreement is to be consistent with the KCRC Ordinance.

Appendix 1 - Scope of Works

14. This sets out the elements of the Scope of Works for the West Rail project which are the Essential Public Infrastructure Works, the Reprovisioning, Remedial and Improvement Works and the West Rail Works.

Appendix 2 - Summary of the Baseline Programme

15. This sets out a summary of the Baseline Programme which will form the basis for the preparation by the Corporation of the Baseline Programme itself.

Appendix 3 - Capital Cost Estimate

16. This sets out the estimate of the Capital Cost by the Corporation for the West Rail project for illustrative purposes only.

Appendix 4 - Financial Projections

17. This sets out the financial projections of the Corporation for the West Rail project for illustrative purposes only.