PWSC(1999-2000)35

For discussion
on 2 June 1999

ITEM FOR PUBLIC WORKS SUBCOMMITTEE
OF FINANCE COMMITTEE

HEAD 711 - HOUSING
Territory Development
Civil Engineering - Land development
561CL -Tin Shui Wai further development - remaining engineering infrastructure and site formation works
    Members are invited to recommend to Finance Committee the upgrading of 561CL to Category A at an estimated cost of $768.8 million in money-of-the-day prices for the remaining engineering works of Tin Shui Wai further development.
PROBLEM

We need to complete the remaining engineering infrastructure and site formation works in the Reserve Zone (RZ) to support further development of Tin Shui Wai (TSW) to cope with the demand for more housing sites.

PROPOSAL

2. The Director of Territory Development (DTD), with the support of the Secretary for Housing, proposes to upgrade 561CL to Category A at an estimated cost of $768.8 million in money-of-the-day (MOD) prices for the remaining engineering infrastructure and site formation works in the RZ of TSW.

PROJECT SCOPE AND NATURE

3. The original project scope of 561CL covers the entire range of new engineering infrastructure in the RZ and the Development Zone (DZ) that is required to service proposed further housing developments in TSW. In February 1998, Finance Committee approved the upgrading of a major part of 561CL to Category A as 563CL (see paragraph 19 below). The remaining scope of 561CL we now propose to upgrade to Category A covers the works in north-eastern RZ and north of Tin Wah Road to the west of the Western Drainage Channel (WDC) which comprise -

  1. site formation of Areas 114, 118, 119 and 121 to 123 (total 74 hectares);

  2. construction of Road D3 (a dual two-lane carriageway of about 1.5 kilometres long);

  3. construction of two vehicular bridges (about 540 metres and 100 metres long respectively) and one pedestrian/cyclist bridge (about 100 metres long) across the WDC;

  4. construction of a promenade with a cycle track;

  5. ancillary drains, sewers, concrete lining to a section of the WDC, and landscaping works;

  6. construction of a wetland (36 hectares) and associated woodland (30 hectares); and

  7. environmental monitoring and audit programme for items (a) to (f) above.
JUSTIFICATIONS

4. The Administration decided in 1994 to further develop TSW as a major area for additional housing supply. In this regard, we have designated about 23 hectares of land in the DZ and about 70 hectares of land (out of a total area of 213 hectares) in the RZ for further development into residential areas. Upon full development by 2003, these areas will provide some 62 500 housing units to accommodate a population of about 190 000 people. In order to cater for the proposed additional developments in TSW, we need to provide the necessary infrastructure in step with the phased completion of the building development.

5. We started the construction of a major part of the engineering infrastructure works under 563CL in mid 1998. These will be completed in phases from August 1999 to end 2001 to serve the early occupation of the housing sites in the RZ. As population builds up, we need to construct Road D3 at the western periphery of the RZ. This road will serve as a district distributor road that provides an alternative and more direct external access link for the developments at the north of the RZ. In conjunction with the construction of Road D3, we need to construct two vehicular bridges and one pedestrian/cyclist bridge, a promenade and a cycle track.

6. Development of the RZ has filled up some freshwater habitats in an old river channel and a short section of the Eastern Temporary Channel. To compensate for the ecological habitats lost, we will provide a 36 hectare constructed wetland in Area 114 and part of Area 118 of the RZ. In addition, we will plant woodlands in Areas 118 and 119, hydroseed Areas 122 and 123 and form a government, institution and community site in Area 121. As well as providing varied habitats for native flora/fauna and attracting particular species of birds, the constructed wetland and woodlands will act as a buffer zone to reduce human disturbance to the birds feeding in the Mai Po Marshes Nature Reserve nearby. The constructed wetland will incorporate a reed-bed system1 which will provide a treatment function and remove a portion of the pollutants present in the stormwater runoff before discharging into Deep Bay.

7. We will retain the existing WDC in the RZ in its current unlined form to preserve important ecological habitats. However, we will provide a concrete bed to a 500 metre long section of channel directly downstream of the existing inflatable dam near Tin Wah Road. This will facilitate maintenance and clearance of this part of the channel as debris and tidal deposits are most prone to accumulate at this location.

FINANCIAL IMPLICATIONS

8. We estimate the capital cost of the project to be $768.8 million in MOD prices (see paragraph 9 below), made up as follows -

$ million
(a) Site formation works32.0
(b) Roadworks43.0
(c) Drainage works and concrete bed lining of the WDC44.0
(d) Vehicular and pedestrian/ cyclist bridges294.0
(e) Constructed wetland125.0
(f) Landscaping works24.0
(g) Environmental monitoring and audit4.0
(h) Consultants' fees for68.0
    (i) construction stage
8.0
    (ii) resident site staff costs
60.0
(i) Contingencies63.0
------
Sub-total697.0(at December
1998 prices)
(j) Provision for price adjustment71.8
------
Total768.8(in MOD prices)
------

Owing to insufficient in-house resources, DTD proposes to employ consultants to supervise the proposed works. A breakdown by man months of the estimate for consultants' fees is at the Enclosure.

9. Subject to approval, we will phase the expenditure as follows -

Year$ million
(Dec 1998)
Price
adjustment
factor
$ million
(MOD)
1999 - 200045.01.0262546.2
2000 - 2001160.01.06217169.9
2001 - 2002257.01.09934282.5
2002 - 2003180.01.13782204.8
2003 - 200440.01.1776547.1
2004 - 200515.01.2188618.3
------------
697.0768.8
------------

10. We have derived the MOD estimate on the basis of the Government's latest forecast of trend labour and construction prices for the period from 1999 to 2005. We will tender the proposed works under a standard remeasurement contract because the works involve extensive earthworks, the quantities of which may vary according to the actual ground conditions. The contract will provide for price adjustments as the contract period will exceed 21 months.

11. We estimate the annually recurrent expenditure to be $10.66 million.

PUBLIC CONSULTATION

12. We consulted the Traffic and Transport Committee of the Yuen Long District Board on the Final Investigation Report of the TSW further development project on 7 January 1997. Members had no objection to the proposed works.

13. On 23 January 1997, we consulted the Environmental Improvement Committee of the Yuen Long District Board on the findings of the Environmental Impact Assessment (EIA) study in respect of the engineering infrastructure project for TSW further development. Members had no adverse comments on the findings.

14. We gazetted the proposed concrete lining work for a section of the WDC under the Foreshore and Sea-bed (Reclamations) Ordinance on 16 January 1998 and received no objections. The Chief Executive in Council authorized the proposed works on 26 March 1998. We also gazetted the proposed road scheme under the Roads (Works, Use and Compensation) Ordinance on 27 March 1998 and received no objections. The Secretary for Transport authorized the roadworks on 12 June 1998.

ENVIRONMENTAL IMPLICATIONS

15. Under the Environmental Impact Assessment (EIA) Ordinance, Road D3 is a designated project which requires an environmental permit (EP) for construction and operation. The channel lining works for the WDC has been exempted from designation by the virtue of the authorization under the Foreshore and Sea-bed (Reclamations) Ordinance on 26 March 1998.

16. We completed an EIA study in March 1997 to assess the environmental impacts of the construction and operation of the entire engineering project for the TSW further development. On 21 April 1997, the Advisory Council on the Environment (ACE) endorsed the findings and recommendations of the EIA report. As the proposed works will not cause adverse long term environmental impacts, long term mitigation measures are not required. During the construction period, we shall control dust, noise, site run-off and odour impacts to within established standards and guidelines by incorporating and enforcing appropriate environmental control clauses in the contract.

LAND ACQUISITION

17. We have resumed about 0.56 hectare of agricultural land. The land acquisition and clearance will affect one domestic structure with four residents. The Director of Housing will offer the eligible families accommodation in public housing in line with the existing policy. We will charge the cost of land acquisition and clearance, estimated at $12.5 million, to Head 701 - Land Acquisition.

BACKGROUND INFORMATION

18. We upgraded 561CL to Category B in June 1997.

19. In February 1998, Finance Committee approved the upgrading of part of 561CL to Category A as 563CL "Tin Shui Wai further development - road junction improvement, site formation and main engineering infrastructure" at an estimated cost of $3,163.2 million in MOD prices. We started the works in July 1998 for completion in phases from August 1999 to end 2001.

20. We engaged consultants in August 1997 to undertake the detailed design for the project under 562CL "Tin Shui Wai further development - engineering infrastructure and remaining site formation works: consultants' fees and site investigation". The consultants have substantially completed the detailed design and drawings for the remaining works under 561CL. We plan to start the proposed works in October 1999 for completion in mid 2003.

----------------------------------------

Housing Bureau
May 1999

Enclosure to PWSC(1999-2000)35

561CL - Tin Shui Wai further development - remaining engineering
infrastructure and site formation works

Breakdown of the estimate for consultants' fees

Consultants' staff costs Estimated
man
months
Average
MPS*
salary
point
Multiplier
factor
Estimated
fee
($ million)
(a) Consultants' fees for construction stage
    (i) contract administration
Professional
Technical
33
20
40
16
2.4
2.4
5.0
1.0
(ii) preparation of as-built drawings Professional
Technical
6
22
40
16
2.4
2.4
0.9
1.1
(b)Resident site staff costsProfessional
Technical
250
932
40
16
1.7
1.7
26.7
33.3
-----
Total consultants' staff costs68.0
-----

* MPS = Master Pay Scale

Notes

1. A multiplier factor of 2.4 is applied to the average MPS point to arrive at the full staff costs including the consultants' overheads and profit, as the staff will be employed in the consultants' offices. A multiplier factor of 1.7 is applied in the case of site staff supplied by the consultants. (At 1.4.98, MPS pt. 40 = $62,780 p.m. and MPS pt. 16 = $21,010 p.m.)

2. The figures given above are based on estimates prepared by the Director of Territory Development. The consultancy works for this project have been included as part of the overall consultancy agreement for the Tin Shui Wai further development. We will negotiate the consultants' fees and resident site staff costs with the consultants after funding approval.

1.A reed-bed system in a wetland comprises a specified type of reed and soil. The dimensions of the bed, height of water and rate of flow are designed so as to remove organic and metal pollutants.