    Members are invited to recommend to Finance Committee the upgrading of 201EP to Category A at an estimated cost of $100 million in money-of-the-day prices for the construction of a 30-classroom primary school in area 101, Tin Shui Wai, Yuen Long.

PROBLEM

There are not enough primary schools in Yuen Long District to meet the increase in demand for school places.

PROPOSAL

2. The Director of Architectural Services (D Arch S), with the support of the Secretary for Housing and the Secretary for Education and Manpower, proposes to upgrade 201EP to Category A at an estimated cost of $100 million in money-of-the-day (MOD) prices for the construction of a primary school in area 101, Tin Shui Wai, Yuen Long.

PROJECT SCOPE AND NATURE

3. The proposed primary school is a standard design 30-classroom school building. It will have -

  1. 30 classrooms;

  2. six special rooms, including a computer-assisted learning room and a language room;

  3. four remedial teaching rooms;

  4. a guidance activity/interview room;

  5. two interview rooms;

  6. two staff rooms and a staff common room;

  7. a student activity centre;

  8. a conference room;

  9. a library;

  10. an assembly hall;

  11. a multi-purpose area; and

  12. ancillary accommodation including a lift and relevant facilities for the handicapped.

JUSTIFICATION

4. To meet the increase in demand for primary school places and to help achieve the policy target of enabling 60% of pupils in public sector schools to study on a whole-day basis by the commencement of the school year 2002/03, the Director of Education (D of E) has been making plans to construct an additional 73 primary schools for completion by August 2002. To date, five of these schools have been completed, 40 school projects have been upgraded to Category A and are at various stages of construction.

5. Yuen Long District now has 45 public sector primary schools providing 674 classrooms. D of E forecasts that an additional 508 classrooms will be required to meet the increase in demand for school places by the school year 2002/03. Ten primary schools providing 300 classrooms have already been upgraded to Category A and planned for completion in the school year 2001/02. 201EP will further reduce the shortfall by 30 classrooms to 178 classrooms. The remaining shortfall will be met by other school projects which are currently being planned.

6. The public housing development at Tin Shui Wai Area 101 will produce about 9 000 housing flats for a population intake of 30 000 in 2001. 201EP will meet the demand from the population of the area and will also reduce the district shortfall by 30 classrooms.

FINANCIAL IMPLICATIONS

7. We estimate the capital cost of the project to be $100 million in MOD prices (see paragraph 8 below), made up as follows -


$ million


(a) Piling

11.3


(b) Building

52.0


(c) Building services

12.0


(d) Drainage and external works

9.0


(e) contingencies

8.4



______


Sub-total

92.7

(at December
1998 prices)

(f) Provision for price adjustment

7.3



______


Total

100.0

(in MOD prices)


______


The construction floor area of 201EP is 10 727 square metres. The construction unit cost, represented by building and building services costs, is $5,966 per square metre at December 1998 prices. D Arch S considers this construction unit cost reasonable. A comparison of the standard cost of a primary school with the project estimate of this school is at the Enclosure.

8. Subject to approval, we will phase the expenditure as follows -

Year$ million
(Dec 1998)
Price
adjustment
factor
$ million
(MOD)

1999 - 2000

4.4

1.02625

4.5

2000 - 2001

50.5

1.06217

53.6

2001 - 2002

28.4 1.09934 31.2

2002 - 2003

9.4

1.13782

10.7

______ ______
92.7 100.0
______ ______

9. We derived the MOD estimates on the basis of Government's latest forecast of trend labour and construction prices for the period 1999 to 2003. We will tender the works under fixed-price lump-sum contract because we can clearly define the scope of works in advance, leaving little room for uncertainty.

10. The cost of furniture and equipment, estimated to be $4.2 million, will be borne by the school sponsor as the school will be allocated for operating as a new aided school. We estimate the additional annually recurrent expenditure for the school to be $19.5 million.

PUBLIC CONSULTATION

11. We consulted the Social Services and Publicity Committee of the Yuen Long Provisional District Board in March 1999. Members of the Committee supported the project.

ENVIRONMENTAL IMPLICATIONS

12. Based on the Preliminary Environment Review completed by D Arch S in December 1998, the Director of Environmental Protection agrees that the proposed school would not be subject to any adverse environmental impacts. We will control noise, dust and site run-off nuisances during the construction through the implementation of appropriate mitigation measures in the relevant contracts.

LAND ACQUISITION

13. The project does not require any land acquisition.

BACKGROUND INFORMATION

14. We upgraded 201EP to Category B in May 1997. D Arch S has completed site investigations for the project and is in the process of preparing the detailed working drawings and tender documents using in-house staff resources. We plan to start the construction works in November 1999 for completion in May 2001.

--------------------------------------

Housing Bureau
April 1999

(PWSC0116/WIN4)

Enclosure to PWSC(1999-2000)7

A comparison of the standard cost of a 30-classroom primary school project
with the estimated cost of 201EP


Standard
cost*

201EP



$ million
(at Dec 1998 prices)


(a) Piling

9.5

11.3

(See note A)

(b) Building

52.0

52.0


(c) Building services

12.0

12.0


(d) Drainage and external works

9.0

9.0


(e) Contingencies

8.3

8.4

Total

90.8

92.7


(f) Construction floor area

10 727m2

10 727m2


(g) Construction unit cost
{[(b)+(c)] |(f)}

$5,966/m2

$5,966/m2


* Assumptions for standard cost

1. The estimation is based on the assumption that the school site is uncomplicated and without abnormal environmental restrictions. No allowance is reserved for specific environmental restrictions such as the provision of insulated windows, air-conditioning and solid boundary walls to mitigate noise impacts on the school.

2. No site formation works/geotechnical works are required as they are normally carried out by other government departments under a separate engineering vote before the handing-over of the project site for school construction.

3. Piling cost is based on the use of 112 numbers of steel H-piles at an average depth of 30 metres, on the assumption that percussive piling is permissible. It also includes costs for pile caps, strap beams and testing. No allowance is reserved for the effect of negative skin friction due to fill on reclaimed land.

4. Cost for drainage and external works is for a standard 30-classroom primary school site area of 6 200 square metres built on an average level site without complicated geotechnical conditions, utility diversions, etc. (i.e. a greenfield site).

5. No consultancy services are required.

6. Furniture and equipment costs are excluded as they are usually borne by the sponsoring body of an aided school.

7. The standard cost for comparison purpose is subject to review regularly. We have recently updated the standard cost of a primary school from $85.3 million at December 1997 prices to $90.8 million at December 1998 prices. The updated standard cost estimate also reflects a minor increase in the construction floor area of a primary school from 10 526 square metres to 10 727 square metres. We will continue to review periodically, and revise if necessary, the standard cost which should be adopted for future projects.

Note

A. The piling cost is higher because it is based on the provision of 112 numbers of steel H-piles at average depth of 35 metres instead of 30 metres in a standard school.