For discussion FCR(95-96)90
on 8 December 1995

ITEM FOR FINANCE COMMITTEE

CAPITAL WORKS RESERVE FUND
HEAD 708 - CAPITAL SUBVENTIONS AND MAJOR SYSTEMS AND EQUIPMENT
Education Subventions
Subhead 8011EC Noise abatement programme in schools, stage III

Members are invited to approve an increase in the project estimate from $217.8 million by $35 million to $252.8 million money-of-the-day prices for completing implementation of noise abatement measures in 239 aided schools in the third stage of the noise abatement programme in schools.



PROBLEM

The approved project estimate is insufficient to complete the implementation of noise abatement measures in all the 239 aided schools included in the third stage of the noise abatement programme (the programme).

PROPOSAL

2. The Director of Education (D of E) proposes to increase the project estimate for the programme from $217.8 million by $35 million to $252.8 million.

JUSTIFICATION

3. In the course of carrying out the programme, the Director of Environmental Protection (DEP) re-assessed the noise pollution levels at schools identified for improvement to take account of the changing traffic condition and its consequential impact on the schools. As a result of the re-assessment, DEP pollution levels at the schools identified for improvement under the third stage of NAPIS, the Director of Environmental Protection (DEP) has identified more rooms in some of the schools which require installation of noise abatement measures. This has increased the number of rooms requiring insulation from 3 309 to 4 420, comprisingtraffic noise requiring improvement work are listed in Enclosure 1. 3 250 classrooms, 920 special rooms and 250 staff rooms.

4. To date, we have completed the works for 217 schools at a cost of $198.6 million. The balance of $19.2 million is insufficient to cover the cost of the works for the remaining 22 schools as listed at the Enclosure2.

FINANCIAL IMPLICATIONS

5. The Director of Architectural Services estimates that the cost for the remaining works is $54.2 million. D of E therefore proposes to increase the project estimate to $252.8 million, calculated as follows -

$

Cost of remaining works

54,200,000

Less

Balance of approved project estimate

19,200,000

Shortfall

35,000,000

Add

Approved project estimate

217,764,963

Revised project estimate

252,764,963

Say

252.8 million

6. If Members approve this proposal, we expect the remaining works to be completed by Easter 1996. The cashflow of the project is as follows -

Year

$ million

1994-95 (Actual)

106.9

1995-96

70.0

1996-97

70.0

1997-98

5.9

Total

252.8

7. D of E estimates that there will be an additional annually recurrent cost of $6.8 million arising from the additional rooms that need to be insulated under the programme. This will be met through the Secretary for Education and Manpower’s allocation on education subventions.

BACKGROUND INFORMATION

8. On 16 April 1993, Members approved a project estimate of $217.8 million for implementing noise abatement measures in 239 aided schools under the third stage of the noise abatement programme. The then estimate of the project was based on the cost of introducing noise abatement measures to 3 309 rooms comprising 2 449 classrooms, 677 special rooms and 183 staff rooms.

Education and Manpower Branch
November 1995


Enclosure to FCR(95-96)90

Noise Abatement Programme in Schools, Stage III Remaining Works


School Number of
classrooms
Number of special rooms Number of staff rooms Estimated capital cost

Wanchai District

1.

Lingnan Middle School

12

2

1

1,243,300

Kowloon City District

2.

Chan Sui Ki (La Salle) College

9

1

0

817,400

3.

Hoi Ping Chamber of Commerce
Secondary School

24

0

2

2,003,400

4.

Notre Dame College

9

9

1

2,706,700

5.

Wa Ying College

12

5

0

2,382,800

6.

YWCA Hioe Tjo Yoeng College

17

8

2

2,428,000

Kwun Tong District

7.

Po Chiu College

19

6

0

3,045,400

8.

Bishop Hall Memorial Prevocational
School

8

3

1

1,054,500

9.

Kei Chi Middle School

11

11

3

3,248,900

Sham Shui Po District

10.

Buddhist Tai Hung College

20

0

0

2,398,000

Wong Tai Sin District

11.

Kit Sam Middle School

25

9

2

4,018,000

Yau Ma Tei District

12.

Lutheran Middle School

19

4

0

2,803,800

North District

13.

Fung Kai No. 1 Secondary School

14

0

0

1,933,600

Sai Kung District

14.

Sai Kung Central Primary School

4

0

2

455,400

Tuen Mun District

15.

The Sam Shing Chuen Lau Ng Ying
Primary School

24

2

2

2,209,600

16.

Madam Lau Kam Lung Secondary
School of MFBM

23

0

1

1,853,100

17.

Tsung Tsin College

0

9

0

1,087,200

18.

Christian Alliance College

27

6

2

2,960,400

Tai Po District

19.

Immanuel Lutheran College

24

6

2

2,728,200

Tsuen Wan District

20.

St. Francis Xavier’s School

19

6

1

2,268,300

21.

Carmel Alison Lam Foundation
Secondary School

6

13

0

2,884,800

22.

SKH Li Ping Secondary School

12

8

0

2,745,200

Total

338

108

22

49,276,000

Contingency (10% of project cost)

4,927,600

Total

54,203,600

Say

54,200,000


Last Updated on 2 December 1998