FCR(98-99)27

For discussion
on 18 September 1998

ITEM FOR FINANCE COMMITTEE

RECOMMENDATIONS OF THE PUBLIC WORKS SUBCOMMITTEE
ON PUBLIC WORKS PROGRAMME AND SUBVENTION PROJECTS

At the Enclosure is a summary of the recommendations of the Public Works Subcommittee (PWSC) made at its meeting on 4 September 1998. The relevant papers have previously been forwarded to all Members for consideration by the PWSC and are therefore not enclosed.

2. Members are invited to approve the PWSC recommendations.


--------------------------------------------


Finance Bureau
September 1998


Enclosure to FCR(98-99)27


Summary of the Recommendations
of the Public Works Subcommittee
made at its meeting on 4 September 1998


Project code Project description Recommendation

126TB
PWSC(98-99)1
(Head 706)

Pedestrian subway at junction of Austin Road/Canton Road

To recommend to Finance Committee the upgrading of 126TB to Category A at an estimated cost of $90.2 million in money-of-the-day prices for constructing a pedestrian subway at the junction of Austin Road/Canton Road.

405CL
PWSC(98-99)3
(Head 705)

Pak Shek Kok reclamation for dumping, stage 3

To recommend to Finance Committee the upgrading of 405CL, retitled "Pak Shek Kok reclamation for public filling, stage 3", to Category A at an estimated cost of $240.8 million in money-of-the-day prices.

437CL
PWSC(98-99)4
(Head 707)

Roadworks in Aldrich Bay reclamation area

To recommend to Finance Committee the upgrading of 437CL to Category A at an estimated cost of $283.1 million in money-of-the-day prices for the provision of roads, drains and essential infrastructure in the Aldrich Bay reclamation area.

643TH
PWSC(98-99)6
(Head 711)

Trunk Road T7 in Ma On Shan

To recommend to Finance Committee -

(a) the upgrading of part of 643TH, as B648TH entitled "Trunk Road T7 in Ma On Shan - detailed design and site investigations", to Category A at an estimated cost of $66.7 million in money-of-the-day prices; and

(b) the retention of the remainder of 643TH in Category B.

580TH
PWSC(98-99)8
(Head 706)

Tsing Yi North Coastal Road

To recommend to Finance Committee the upgrading of 580TH to Category A for the construction of the Tsing Yi North Coastal Road at an estimated cost of $1,604.4 million in money-of-the-day prices.

13EJ
PWSC(98-99)9
(Head 708)

Student hostel, phase 1 (806 places)
City University of Hong Kong

To recommend to Finance Committee to approve a new commitment of $271.02 million in money-of-the-day prices for the construction of phase 1 of the student hostel project of the City University of Hong Kong.