  1. the upgrading of part of 205DS entitled Aberdeen, Ap Lei Chau and Pok Fu Lam sewerage, stage 1B works" to Category A at an estimated cost of $530 million in money-of-the-day prices; and
  2. the retention of the remainder of 205DS in Category B.

PROBLEM

The existing sewerage systems in Aberdeen, Ap Lei Chau and Pok Fu Lam do not have adequate capacity to serve these areas.

PROPOSAL

2. The Director of Drainage Services, with the support of the Secretary for Planning, Environment and Lands, proposes to upgrade part of 205DS to Category A at an estimated cost of $530 million in money-of-the-day (MOD) prices for the construction of the Aberdeen, Ap Lei Chau and Pok Fu Lam stage 1B sewerage works.

PROJECT SCOPE AND NATURE

3. Project 205DS Aberdeen, Ap Lei Chau and Pok Fu Lam sewerage", comprising two stages of works, aims at improving the existing sewerage systems in the Aberdeen, Ap Lei Chau and Pok Fu Lam areas. The part of the project we now propose to upgrade to Category A is stage 1B works which comprises -

  1. the construction of 2.7-kilometre long trunk sewers (525 to 1 500 millimetres in diameter) from Wong Chuk Hang to the Aberdeen preliminary sewage treatment works and 2-kilometre long associated branch sewers (150 to 1 050 millimetres in diameter);

  2. the demolition and reprovisioning of a sewage pumping station and modification works at the Aberdeen preliminary sewage treatment works;

  3. the construction of 500-metre long sewers (150 to 525 millimetres in diameter) in Ap Lei Chau; and

  4. the rectification of expedient connections during the sewers upgrading works.
4. The remainder of 205DS, comprising the surveys, site investigations, detailed design and construction for the remaining stage 1 works and the stage 2 works, will be retained in Category B. Details of the works are as follows -
  1. stage 1 works (remainder) -

    1. the refurbishment and reprovisioning of sewerage in the Aberdeen Reservoir water gathering ground; and

    2. the upgrading of the Wah Fu and Ap Lei Chau sewage screening plants.


  2. stage 2 works -

    1. the upgrading of sewers and the construction of a pumping facility in Shum Wan Road; and

    2. the survey and rectification of expedient connections in Aberdeen, Ap Lei Chau and Pok Fu Lam as well as minor sewerage improvement works in these areas.

JUSTIFICATION

5. In June 1995, we completed the sewerage master plan study for Aberdeen, Ap Lei Chau and Pok Fu Lam under 149DS "Aberdeen, Ap Lei Chau and Pok Fu Lam sewerage - consultants’ fees and investigation". The study identified deficiencies in the existing sewerage systems and recommended improvement measures to the systems in order to provide sufficient capacity to meet the sewage flow demand of a population of about 290 000 by 2011 in these areas.

6. The trunk sewers from Wong Chuk Hang (along Wong Chuk Hang Road, Aberdeen Praya Road and Tin Wan Praya Road) to the Aberdeen preliminary sewage treatment works and the associated branch sewers (in Heung Yip Road, Nam Long Shan Road, Yip Kan Street and Shek Pai Wan Road), which were built many years ago, do not have sufficient capacity to deal with the current sewage flow which has increased in line with the development in the areas over the years. Furthermore, since the gradient of these sewers is not steep, solid particles may settle in the sewers, causing siltation and further reducing their capacity. More seriously, spillage of sewage through manholes may occur and cause flooding, environmental nuisance and inconvenience to road users. We need to reconstruct these sewers at a steeper gradient to facilitate self-cleansing of the sewers and to provide sufficient capacity to cater for the sewage flow demand up to 2011.

7. To handle the sewage coming from steeper sewers and to cope with the increasing sewage flow demand up to 2011, we need to reconstruct the sewage pumping station and to upgrade the facilities in the Aberdeen preliminary sewage treatment works.

8. With regard to the sewers in Ap Lei Chau, we have identified that the existing sewers around Ap Lei Chau Main Street and two sections of sewers at Lei Tung Estate Road and Lei Nam Road are susceptible to siltation. We have also observed that the sewers around Ap Lei Chau Main Street are, at some locations, connected to the stormwater drains, allowing via the drains direct discharge of sewage to the sea, without treatment. To rectify the situation, we plan to reconstruct these sewers at a steeper gradient and cut off the connections between the sewers and the stormwater drains.

FINANCIAL IMPLICATIONS

9. We estimate the capital cost of the proposed works to be $530 million in MOD prices (see paragraph 10 below), with details as follows -



$ million


(a) Trunk sewers from Wong Chuk Hang to the Aberdeen preliminary sewage treatment works and associated branch sewers


176.7


(b) Sewage pumping station and modification works in the Aberdeen preliminary sewage treatment works


131.3


(i) civil engineering works

89.2



(ii) electrical and mechanical works

42.1



(c) Sewers in Ap Lei Chau and rectification of expedient connections


6.4


(d) Consultants’ fees


50.2

(i) construction stage

2.2



(ii) resident site staff cost

48.0



(e) Contingencies


33.6




______


Sub-total


398.2

(at December

1997 prices)

(f) Inflation allowance


131.8




______


Total


530.0

(in MOD prices)



______


A breakdown by man months of the estimates for consultants’ fees is at the Enclosure.

10. Subject to approval, we will phase the expenditure as follows -

Year

$ million

(Dec 1997)

Price

adjustment

factor

$ million

(MOD)

1999 - 2000

60.0

1.14878

68.9

2000 - 2001

110.0

1.24642

137.1

2001 - 2002

160.6

1.35237

217.2

2002 - 2003

41.1

1.46732

60.3

2003 - 2004

29.2

1.59204

46.5


______


______


400.9


530.0


______


______

11. We have derived the MOD estimate on the basis of the Government's forecasts of trend labour and construction prices for the period 1999 to 2004. We will tender the electrical and mechanical works under a lump sum contract because we can clearly define the scope of major part of the works. The contract will allow for adjustments to the tender price due to inflation as the contract period will exceed 21 months.

12. We will tender the civil engineering works under a standard remeasurement contract because we are uncertain about the existence and the exact locations of underground utilities such as electric cables, telephone lines and water mains. The contract will also allow for adjustments to the tender price due to inflation as the contract period will exceed 21 months.

13. We estimate the additional annually recurrent expenditure arising from the proposed works to be $1.14 million.

14. Based on the current level of expenditure on operation and maintenance of sewerage facilities, the proposed works by itself would lead to an increase in the recurrent cost of providing sewage services of about 0.2 % which will need to be taken into account in determining sewage charges. [ Sewage charges are determined by the recurrent cost of providing sewage services to the community as a whole and the level of subsidy from the General Revenue. The Administration is currently considering various options on the level of subsidy and will consult the relevant LegCo Panels before any decision is made.1

PUBLIC CONSULTATION

15. We consulted the Works Projects Committee of the Provisional Southern District Board on 15 September 1997 on the whole stage 1 works, including the proposal for temporary traffic arrangements and environmental mitigation measures to be adopted during construction. Members of the Provisional District Board supported the implementation of the proposed works.

ENVIRONMENTAL IMPLICATIONS

16. The Director of Environmental Protection completed an environmental review in 1995 and concluded that the project would have no major long term environmental impact. No environmental impact assessment is therefore necessary. We will control noise, dust and site run-off during construction to within established standards and guidelines through the implementation of mitigation measures in the relevant contracts.

LAND ACQUISITION

17. This project does not require any land acquisition.

BACKGROUND INFORMATION

18. In September 1995, we upgraded 205DS to Category B for the sewerage improvement works for Aberdeen, Ap Lei Chau and Pok Fu Lam. We plan to carry out the works in two stages.

19. To facilitate the implementation of 205DS in conjunction with the road works, we have packaged the stage 1 works into sub-stages. In February 1998, Finance Committee approved the upgrading of part of 205DS to Category A, as 322DS "Aberdeen, Ap Lei Chau and Pok Fu Lam sewerage, stage 1A works" with an approved project estimate of $71.8 million in MOD prices for the stage 1A works. We started these works in July 1998 for completion in September 2001.

20. We have completed the detailed design and tender documents for the stage 1B works. We plan to start the works in March 1999 for completion in December 2001.

21. We plan to start the remaining stage 1 works in late 2000 for completion in mid 2002. We also plan to start the stage 2 works in 2001 for completion in 2004.

-------------------------------------

Planning, Environment and Lands Bureau

September 1998

(PWSC0012/WIN1)

Enclosure to PWSC(98-99)24

205DS - Aberdeen, Ap Lei Chau and Pok Fu Lam sewerage
Breakdown of estimates for consultants’ fees

Consultants’ staff costs


Estimated
man-
months

Average
MPS
salary
point

Multiplier
factor

Estimated
fee
($ million)

(a) Consultants’ fees for construction stage

Professional
Technical

7.5
14.5

40
16

3.0
3.0

1.33
0.86

(b) Site supervision by resident site staff employed by the consultants

Professional
Technical

167.5
651.0

40
16

2.1
2.1

20.83
27.15






______



Total consultants’ staff costs

50.17






______

Notes

(1) A multiplier factor of 3 is applied to the average MPS point to arrive at the full staff costs including the consultants’ overhead and profit, as the staff will be employed in the consultants’ offices. A multiplier factor of 2.1 is applied in the case of site staff supplied by the consultants. (At 1.4.97, MPS pt. 40 = $59,210 p.m. and MPS pt. 16 = $19,860 p.m.)

(2) The figures given above are based on actual fee proposal from the consultants undertaking the investigations, design and construction supervision.

(PWSC0012/WIN1)

1Sewage charges are determined by the recurrent cost of providing sewage services to the community as a whole and the level of subsidy from the General Revenue. The Administration is currently considering various options on the level of subsidy and will consult the relevant LegCo Panels before any decision is made.