ItemPaper No.SubjectDecisions
1.FCR(2018-19)89 RECOMMENDATIONS OF THE ESTABLISHMENT SUBCOMMITTEE MADE ON 22 FEBRUARY 2019

Approved
(Division ordered -
Yes - 36
No - 2
Abstention – 4)

EC(2018-19)22
  • Creation of one supernumerary post of Senior Principal Executive Officer (D2) in the Food and Environmental Hygiene Department for the implementation of the regulatory regime on private columbaria
 
2.FCR(2019-20)3 RECOMMENDATION OF THE PUBLIC WORKS SUBCOMMITTEE MADE ON 20 MARCH 2019

Under deliberation

PWSC(2018-19)41
  • Advance site formation and engineering infrastructure works at Kwu Tung North new development area and Fanling North new development area
    First stage of site formation and engineering infrastructure at Kwu Tung North new development area and Fanling North new development area
    Remaining phase of site formation and engineering infrastructure works at Kwu Tung North new development area and Fanling North new development area
    Site formation and infrastructure works for Police facilities in Kong Nga Po
    Shek Wu Hui Effluent Polishing Plant
    Special Ex-gratia Cash Allowance for the Kwu Tung North and Fanling North New Development Area
 
3.FCR(2018-19)88 HEAD 63 – HOME AFFAIRS DEPARTMENT
Subhead 000 Operational expenses
Subhead 700 General non-recurrent
New item "Reimbursement of Setting-up Expenses and Winding-up Expenses for District Council members of the 2020-2023 term"


Not dealt with
4.FCR(2018-19)91 RECOMMENDATION OF THE ESTABLISHMENT SUBCOMMITTEE MADE ON 22 FEBRUARY 2019

Not dealt with

EC(2018-19)23
  • Retention of two supernumerary posts of one Administrative Officer Staff Grade C (D2) in the Security Bureau and one Assistant Director of Immigration (GDS(C)2) in the Immigration Department to continue steering the comprehensive review of handling non-refoulement claims and to step up relevant measures
 
5.FCR(2018-19)92 RECOMMENDATION OF THE PUBLIC WORKS SUBCOMMITTEE MADE ON 13 FEBRUARY 2019

Not dealt with

PWSC(2018-19)37
  • Widening of western section of Lin Ma Hang Road between Ping Yuen River and Ping Che Road
 
6.FCR(2018-19)93 RECOMMENDATION OF THE PUBLIC WORKS SUBCOMMITTEE MADE ON 20 FEBRUARY 2019

Not dealt with

PWSC(2018-19)39
  • Immigration Headquarters in Tseung Kwan O
 
7.FCR(2019-20)1 RECOMMENDATION OF THE ESTABLISHMENT SUBCOMMITTEE MADE ON 22 MARCH 2019

Not dealt with

EC(2018-19)29
  • Retention of three supernumerary posts of one Principal Government Engineer (D3) and one Administrative Officer Staff Grade C (D2) in the Home Affairs Bureau; and one Chief Engineer (D1) in the Civil Engineering and Development Department to provide continual and dedicated support for monitoring and facilitating the implementation of the West Kowloon Cultural District (WKCD) project and to drive the implementation of the integrated basement and government infrastructure projects in WKCD
 
8.FCR(2019-20)2 RECOMMENDATION OF THE PUBLIC WORKS SUBCOMMITTEE MADE ON 13 FEBRUARY 2019

Not dealt with

PWSC(2018-19)38
  • A 30-classroom primary school at Shui Chuen O, Sha Tin
 
9.FCR(2019-20)4 RECOMMENDATION OF THE PUBLIC WORKS SUBCOMMITTEE MADE ON 20 MARCH 2019

Not dealt with

PWSC(2018-19)32
  • Organic Resources Recovery Centre Phase 2