| Download Full Report
| ||
TABLE OF CONTENTS | ||
| Page
| ||
| Part I | Establishment of the Select Committee and its Work
|
|
| Chapter 1 | Introduction | 1 - 5 |
| Background | 1 - 4 | |
| Establishment of the Select Committee | 4 - 5
| |
| Chapter 2 | Matters relating to the Select Committee | 6 - 26 |
| Membership of the Select Committee | 6 | |
| Terms of reference, areas of study and work plan of the Select Committee | 6 - 10 | |
| Practice and procedure | 10 - 14 | |
| Difficulties encountered by and limitations of the Select Committee | 14 - 25 | |
| Presentation of the report | 25 - 26
| |
| Part II | Findings
|
|
| Chapter 3 | Planning and Site Investigation Stage (May 2000 to January 2010) | 27 - 49 |
| Key dates for the "Planning and Site Investigation Stage" | 27 - 28 | |
| Background information on the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link | 28 - 30 | |
| The Project framework | 30 - 39 | |
| Observations | 40 - 49
| |
| Chapter 4 | Early Construction Stage (January 2010 to April 2013) | 50 - 75 |
| Key dates for the "Early Construction Stage" | 50 - 51 | |
| Chronology of developments | 51 - 60 | |
| Observations | 60 - 75
| |
| Chapter 5 | Difficult Stage (May to October 2013) | 76 - 102 |
| Key dates for the "Difficult Stage" | 76 - 78 | |
| Chronology of developments | 78 - 87 | |
| Observations | 87 - 102
| |
| Chapter 6 | Very Difficult Stage (November 2013 to April 2014) | 103 - 130 |
| Key dates for the "Very Difficult Stage" | 103 - 105 | |
| Chronology of developments | 105 - 115 | |
| Observations | 115 - 130
| |
| Part III | Conclusions and Recommendations
|
|
| Chapter 7 | Conclusions | 131 - 147
|
| Chapter 8 | Recommendations | 148 - 152
|
| Acknowledgement | 153
| |
| Signatures of members of the Select Committee | 155 - 156
| |
| Abbreviations | 159 - 162
| |
| Appendices
| ||
| Appendix 1 | The Government's press releases on "Transcript of remarks by Secretary for Transport and Housing" issued on 15 April 2014
| 165 - 166
|
| Appendix 2 | The MTR Corporation Limited ("the Corporation")'s press release on "Revised Programme for Hong Kong Section of Express Rail Link Project" issued on 15 April 2014
| 167 - 168
|
| Appendix 3 | Membership and terms of reference of the Independent Board Committee and Independent Expert Panel
| 169 - 170
|
| Appendix 4 | Petition jointly presented by Hon WU Chi-wai and Hon Charles Peter MOK
| 171
|
| Appendix 5
| Practice and Procedure of the Select Committee
| 172 - 182
|
| Appendix 6
| Written reply dated 18 February 2015 from the Highways Department ("HyD") to the Select Committee
| 183 - 214
|
| Appendix 7
| Written reply dated 18 February 2015 from the Transport and Housing Bureau ("THB") to the Select Committee
| 215 - 235
|
| Appendix 8
| Written reply dated 5 January 2015 from the Corporation to the Select Committee
| 236 - 239
|
| Appendix 9
| Written reply dated 5 February 2015 from the Corporation to the Select Committee
| 240 - 241
|
| Appendix 10
| Written reply dated 12 February 2015 from the Corporation to the Select Committee
| 242 - 243
|
| Appendix 11 | Written reply dated 17 March 2015 from THB to the Select Committee
| 244 - 247
|
| Appendix 12 | Written reply dated 4 January 2016 from THB to the Select Committee
| 248 - 249
|
| Appendix 13 | Written reply dated 16 October 2015 from the Corporation to the Select Committee
| 250
|
| Appendix 14 | Written reply dated 21 December 2015 from the Corporation to the Select Committee
| 251
|
| Appendix 15
| Written reply dated 8 January 2016 from THB to the Select Committee
| 252
|
| Appendix 16
| List of witnesses who attended the Select Committee to Inquire into the Background of and Reasons for the Delay of the Construction of the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link
| 253 - 254
|
| Appendix 17
| Flowchart on the Government's monitoring mechanism on the construction of the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link project
| 255
|
| Appendix 18
| Membership and terms of reference of Project Supervision Committee, Project Coordination Meeting and Contract Review Meeting
| 256
|
| Appendix 19
| Membership and terms of reference of the Project Control Group of the Corporation
| 257
|
| Appendix 20
| Written reply dated 23 December 2015 from Jacobs China Limited to the Select Committee
| 258 - 262
|
| Appendix 21 | Written reply dated 9 June 2015 from HyD to the Select Committee
| 263 - 268
|
| Appendix 22 | Written reply dated 21 December 2015 from the Corporation to the Select Committee
| 269 - 278
|
| Appendix 23 | Written reply dated 26 June 2015 from THB to the Select Committee
| 279 - 286
|
| Appendix 24 | Slide presented at the Subcommittee on Matters Relating to Railways meeting on 5 May 2014
| 287
|
| Appendix 25 | Slide presented at the Subcommittee on Matters Relating to Railways meeting on 22 November 2013
| 288
|
| Appendix 26 | Written reply dated 15 January 2016 from THB to the Select Committee
| 289 - 291
|
| Lists of written evidence/documents
|
| |
| A. | Evidence/documents provided by the Government
| 296
|
| B. | Evidence/documents provided by the Corporation
| 297
|
| C. | Evidence/documents provided by Jacobs China Limited
| 298
|
| D. | Evidence/documents provided by witnesses
| 299 - 300
|
| E. | Documents referred to by the Select Committee
| 301 - 303
|
| Minutes of proceedings
| 307 - 349
| |
| No. | Dates of public hearings | Names of witnesses
|
| 1 | 24 March 2015 | Mr Peter LAU Ka-keung
Director of Highways |
| 2 | 21 April 2015 | Mr Peter LAU Ka-keung
Director of Highways |
| 3 | 28 April 2015 | Mr YAU Shing-mu
Under Secretary for Transport and Housing |
| 4 | 26 May 2015 | Mr Joseph LAI Yee-tak
Permanent Secretary for Transport and Housing (Transport) |
| 5 | 2 June 2015 | Mr WAI Chi-sing
Former Director of Highways |
| 6 | 15 July 2015 | Mr Lincoln LEONG Kwok-kuen
Chief Executive Officer MTR Corporation Limited |
| 7 | 20 October 2015 | Mr Henry CHAN Chi-yan
Principal Government Engineer/Railway Development Highways Department Mr TAM Hon-choi Government Engineer/Railway Development 2 Highways Department |
| 8 | 3 November 2015 | Mr Lincoln LEONG Kwok-kuen
Chief Executive Officer MTR Corporation Limited |
| 9 | 10 November 2015 | Mr Anthony J W KING
Project Director Jacobs China Limited Mr William NG Siu-kee Project Manager Jacobs China Limited |
| 10 | 15 December 2015 | Dr Philco WONG Nai-keung
Projects Director MTR Corporation Limited Mr Mark LOMAS Project Manager - Technical Support MTR Corporation Limited |
| 11 | 21 December 2015 | Professor Anthony CHEUNG Bing-leung
Secretary for Transport and Housing |